Making Progress!
Updated: May 5, 2022
We have started the project and we are well underway. The fusing of the pipe is going on as we write this post in two different locations. Approximately 14,960 feet of the 48" is fused and 12,485 feet of 36". The pipe is fused in 1000 feet lengths and then drug through the canal and then waits to be fused to the next 1000 feet. Pipe from the tunnel by the structure is now buried down to about 3000 North along 3500 West. Clearing and prep work is on going ahead of the crews fusing and laying the pipe to make sure progress is made in a timely manner.